Turbine Testing Stand (TTS) Development
Throughout the Spring 2025 semester, I worked with another student to construct and validate a single-phase AC to 3-phase AC converter for the Streamlining Wind Turbines Collaboratory Project.
- Mechanical Design
- Electronics Design
- Sustainability
- Validation
- Teamwork
- Machining
Project Overview:
- Skills Demonstrated
- Mechanical Design, Electronics Design, Sustainability, Validation, Teamwork, Machining
- Clients
- WindAid Institute (Peru), Messiah University Collaboratory for Strategic Partnerships and Applied Research
Problem Statement
"It would be beneficial to the Streamlining Wind Turbine (SWT) team to create a system that generates 3-phase AC power to simulate power coming from a turbine. With this simulated power, the Turbine Monitoring System (TMS) and the battery can be tested in a controlled environment. Additionally, this interior test design will be quicker to set up and easier to control different power inputs to the system."
Download Test Stand Design Record.pdf
My primary contribution to this project was the design of the adapter plate between the motor and generator. Since the goal was to build this stand using existing hardware as much as possible, I opted to attempt to use the blade attachment bracket already on the generator and the V-belt pulley that was attached to the motor. This required drilling three holes through the pulley, which would then have standoffs run through them to provide a rigid connection. Unfortunately, while assembling this system the first time, the old pulley warped considerably, so a new part needed to be bought to replace it.
Once this system was attached, there was still a great deal of stress on the system since we could not reasonably make our setup completely concentric. To mitigate this issue, I introduced some intentional play in the bolts interfacing the adapter that would allow limited movement without resistance normal to the axis of rotation. This final design, as shown in the results plot above, only makes about 300W, with 500 needed to accurately simulate the generator that will be on the final version, yet still likely powerful enough to perform preliminary testing.