Project Overview

Skills Demonstrated
Process Improvement DFMEA/PFMEA Manufacturing Resin Moulding Leadership Quality Engineering Communication Spanish
Employer
WindAid Institute: the non-profit lighting up lives in the remote communities of Andean Peru

I worked on two main goals, while assisting three build teams: a new blade work instruction, and a test plan to determine the impact of carbon fibres in the blade.

Blade Work Instruction

Before my work, the work instruction was a bullet pointed document with a combination of English and Spanish, and corresponded to moulding equipment no longer in use. I first worked through the actual process being used at WindAid twice, building two blades alongside crews of new volunteers without previous experience. I completed a time study of both builds, and took over a hundred pictures of various steps. I then broke the labour into 72 steps, and noted the equipment, manpower, PPE, and materials needed for each step. I also worked with WindAid's permanent workshop staff to determine appropriate process controls (which had not existed prior) to ensure each blade comes out of the mould conforming to the design.

The finished work instruction breaks each step into a single page, with pictures, clear visual hierarchy, and clear definitions of what must be done and what must be checked to ensure it is done right.

This is a page from the previous work instruction, condensing multiple days of labour into a few bullet points with little context on how to complete the task. Pictures rarely indicate what must be done.

This is a page of the new work instruction, comprising one step that takes about half an hour (one of the longer and more complicated tasks). It clearly lays out equipment and safety, with a visual layout that guides you through the step and process. It provides positive and negative examples, and the "process control" tells you when you are done.

Testing Plan

The WindAid 1.7 blade has been continuously improved over its 10+ year lifespan. As all these changes are implemented, it becomes increasingly important to confirm that the blade still meets its design requirements. While in Peru, I put together a comprehensive mechanical test plan to validate every design change for impact, freewheeling, and steady-state operations. This simple plan only requires a single blade to be repurposed for testing, keeping costs low. Beyond design changes, it also allows comparative testing of blade materials, vendors, and composite stackups for future cost- and time-saving endeavours.

Download Test Plan.pdf